Pulse Assembler · Kanadevia Inova · September 2026
| Study and viewer design | 15–18 k€ |
|---|---|
| Library, 60 to 100 assets | 35–45 k€ |
| 5 pilot plants | 5–6 k€ |
| Assembler, training, documentation | 25–35 k€ |
| Perpetual licence, first year of support | 26–30 k€ |
| Total, one-off | 106–134 k€ |
| Each plant after that | 4 € |
| The whole fleet, 200 plants | ≈ 107–135 k€ |
Paid once. The 200 plants add 800 € of internal time to the total.
| Rebuilding 60 to 100 families in Revit | ≈ 19 k€ |
|---|---|
| Preparing each family for the web | ≈ 24 k€ |
| Nothing else is bought — no tool, no licence | — |
| Before the first plant | ≈ 43 k€ |
| Each plant: 1 h of engineer, then a studio pass | ≈ 1 000 € |
| The whole fleet, 200 plants | ≈ 243 k€ |
Twice the price, and it never stops: every new plant costs again. Plus 200 slots in DE's queue, and no date anyone can commit to. Internal time costed at your own rate.
| Committed today — the study, nothing beyond it | 15–18 k€ |
|---|---|
| Everything: library, 5 pilot plants, assembler, licence | 106–134 k€ |
| Each additional plant, with the assembler | 4 € |
| Each additional plant, in Revit | ≈ 1 000 € |
| …and what it also costs there | one DE slot |
At 4 € a plant, and without asking anyone, the 3D model stops being a project and becomes an option you can put in front of every client. In Revit, every plant costs roughly 1 000 € and a slot in a queue you do not control.
That is the real difference. Not a cheaper way to do the same thing — the only version of it that stays inside your department.